AEIC is part of the USAID-funded
Infrastructure Rehabilitation Program

Click
here for the project website
www.irp-af.com
|
|
|
|
Monthly
Summary of Fuel and Performance
|
|
Reports Kandahar ,Lashkar Gah
and Qalat &NW Kabul |
|
Electricity Generating Station
For June 2008 |
|
|
|
|
LashkarGah
Gen Sets |
|
|
|
|
Fuel and Performance
Category |
NW Kabul
Gen Station |
Kandahar
Gen Sets |
Qalat
Gen Sets |
Aybak Gen Sets |
Total |
|
|
|
|
|
|
|
|
|
|
Fuel Delivered
(Liters) |
4,744,626 |
1,740,203 |
304,878 |
143,575 |
48,647 |
6,981,929
- |
|
|
|
|
|
|
|
|
|
|
Fuel Used
(Liters) |
2,256,820 |
1,033,061 |
295,850 |
99,600 |
29,364 |
3,714,695 |
|
|
|
|
|
|
|
|
|
|
Usable Fuel Available
(Liters) |
7,634,360 |
1,209,247 |
163,158 |
105,005 |
40,000 |
|
|
|
|
|
|
|
|
|
|
Days of Fuel Available |
44.3 |
21.3 |
13.4 |
8.3 |
30 |
|
|
|
|
|
-
|
- |
|
|
|
|
Generation
(MWH) |
4,375 |
3,046 |
740 |
332 |
98 |
8,573 |
|
|
|
|
|
|
|
|
|
|
|
Average Fuel Consumption (Liters/MWH) |
518 |
339.2 |
399.8 |
300 |
300 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Note:
Kandahar, Lashkar-Gah and Qalat Fuel
statistics will be provided on monthly basis, however we
will continue to provide you with daily fuel statistics
of NW Kabul |
Aybak
Power Plant Summary Report June 2008
JUNE 08 summary of power plant productivity
|
Power Plant |
Plant Size |
Total MWHr
Produced |
Total Ltrs
Consumed |
Liters/ MWHr |
Total Hrs of
Operation |
Approx No. of
Customers Serviced |
|
Kandahar |
10MW |
3038.1
|
1,030,140 |
339.1 |
7295 |
35 000 |
|
Lashkargah |
3MW |
736.80 |
294,450 |
399.6` |
1868 |
25 000 |
|
Qalat |
5MW |
331.20 |
99,000 |
299.0 |
990 |
4 000 |
|
Tirin
Kot |
500KW |
N/A |
N/A |
N/A |
450 |
600 |
|
NW Kabul |
45MW |
4,357 |
2,256,820 |
518 |
297.8 |
22000 |
|
Aybak |
1MW |
97.88 |
29,364 |
300 |
284 |
5849 |
|
|