Home
About US
Site Map
Links
 Jobs

Contact-us    

AEIC Logo

Afghan Energy Information Center (AEIC)     

پښتو     دری                                           

                                            AEIC is part of the USAID-funded Infrastructure Rehabilitation Program 

Click here for the project website www.irp-af.com

 
 

 Herat MapHerat

 

11 Diesel generating sets produce a total capacity of 3400 kW. All generating sets have depreciated due to excessive use and damage. As of 2003,40 million kw hare being imported from Iran annually. In May 2004, the new 220 kV line from Turkmenistan to Herat was commissioned with a substation of 2x40 MVA capacity.

 

Diesel Generating Sets -Badghis. Three diesel generating sets were installed to meet the

demand of essential services in Badghis. All the sets have deteriorated or been damaged and require replacement. One unit of 500 kVa from World Bank grant was installed in2004.

Diesel generating-Farah.

 

Six diesel generating sets from Czechoslovakia/EX. USSR were installed to meet the demand of essential services. All have depreciated and require spare parts and or replacement. Estimated cost for rehabilitation is US$ 300,000.

 

Partly Completed Electricity Generation Plant -Selma Project. This US$ 57 million Saudi Arabia-aided project was started in 1974 to meet the regional electricity demand. The irrigation-based project was to produce 40 MW of electricity to cover 40% of construction work. The

housing complex, diversion canal, pen stock canal and excavation were completed. A percentage of work on the earth dam also has been completed. During the war all construction equipment at

the site was damaged or destroyed. Rehabilitation of this project is vital for the region. Completion of the project, which is the only hydroelectric project feasible in the region, would require about US$260 million. This project belongs to the Ministry of Irrigation.

 

Sabzak Thermal Power Plant. In the Master Plan of 1980 a 50 MW plant was envisaged using locally available coal from Sabzak coalmine. An incomplete techno-economic study has been carried out by Czechoslovalua. According to the updated Power Sector Master Plan, the coal at Sabzak has high content of sulfur and is not suitable for power production.

28 Western Region Transmission Lines. Circuits are nonexistent in the region. If electricity, costing 2 cents kWh, is to be imported from Turkmenistan then 100 km of 220 ,110 kV single circuit with a 22011 10120 kV substation would be required. The estimated cost of the project is about US10 million, and was completed using Government budget in May 2004. It is in operation and supplies power to Herat.

 

Western Region Distribution Network -Herat. 50% of the distribution network of 610.4 kV in Herat is destroyed. A plan for a distribution system for Herat and the Salma project were to be simultaneously completed. Plant, including 50 step-down transformers, worth US$4.6 million were imported and are available in Herat. The network voltage is 20/0.4 kV. Completion of the project is allowed for under the World Bank funding. Herat substation capacity is 2x40 MVA and is under operation.

 

.

 

 

 

Back to pervious page

 

 

 

 

 

 

 

 Panjshir Hybrid Power Sys

Click here

"The information provided on this web site is not official U.S. Government information and does not represent the views or positions of USAID or the U.S. Government."

Copyright © 2008 Afghan Energy Information Center

Privacy Policy