Home
About US
Site Map
Links
 Jobs

Contact-us    

AEIC Logo

Afghan Energy Information Center (AEIC)     

پښتو     دری                                           

                                            AEIC is part of the USAID-funded Infrastructure Rehabilitation Program 

Click here for the project website www.irp-af.com

 
 

Old’ Kunduz substation

 

 This sub-station had a capacity of 3.2 MVA, and used step down from 35 kV to 6 kV from Pulikhumri-11. This substation is partly damaged, mainly the protection gear, and requires about US$30,000 for its rehabilitation and updating.

 

 

New’ Kunduz substation.

 This sub-station steps down from 110 kV to 35 kV and 6 kV, and has a capacity of 32 MVA using2 transformers of 16 MVA. The sub-station was built to utilize imported electricity from Tajikistan. In1990 the sub-station was damage. The transformers need to be replaced or repaired together with new switchgear, etc. MWP rehabilitated the transmission line and substation with Government funds which was completed in early 2003.

Transmission Line Tajikistan-Kunduz.

 This 110 kV single circuit line was built on P.C.C. poles. It is badly damaged, needing new insulators and conductor. The cost for rehabilitation is estimated at US$1,200,000, which would increase the capacity to import by 32 MW. The reconstruction work was completed, and the line was re-commissioned in early 2003. Transmission line-‘New’ substation to ‘Old’ substation. The single circuit line transmission voltage 35 kV length 5 km is operational, requiring only proper connections and joints to reduce losses. Repair work is proceeding and MWP expects to re-commission this line in May 2003.

 

 

 

Transmission line Pulikhumri to Kunduz. The single circuit line of 82.4 km, with a transmitting voltage designed for 110 kV and used for 35 kV is completely destroyed. Connection of Pulikhumri-I1 to Kunduz would require US$8 million. This line, if repaired, 24 would be erected as 200 kV instead of 110 kV and would also provide electricity to Baghlan rural areas.

 

Distribution network.

The region had a total network of 333 km having various voltages of 20 kV, 6 kVlO.4 kV. The distribution system suffered 60 % damage, with over 32 km of 20 kV line destroyed. The region had two main distribution networks; Baghlan network, and Kunduz network.

 

.

 

Back to pervious page

 

 

 

 

 

 

 Panjshir Hybrid Power Sys

Click here

"The information provided on this web site is not official U.S. Government information and does not represent the views or positions of USAID or the U.S. Government."

Copyright © 2008 Afghan Energy Information Center

Privacy Policy