Mahipar Hydro Electric Plant

      Mahipar Hydro Electric Plant

This plant is constructed on the Kabul and Logar Rivers at Mahipar, with installed capacity of 66 MW, 3 x 22 MW vertical Francis turbines from Germany. At the moment the plant is operational but lacks spares. Since its commissioning in 1967, the plant has hardly received any servicing. KfW is financing the complete rehabilitation of one unit and modernization of a second unit. The work is ongoing and is expected to be completed in 2006.

Having little storage, Mahipar only operates in winter.  The Season is October through May; Generally, in December through April all three units can run.  As of winter 2007, the turbines work only at 44 MW.  Water is usually available for one unit from the beginning of October; During month of May usually only one unit is running;

 

current status of the plant  is constraint due to  shortage of  water. 28.July.2007

Seasonality of Hydrology at Mahipar

 Seasonality of Hydrology at Mahipar

The rehabilitation of Unit 3 started at the end of summer in very slow process (money, contract, etc), the official schedule for maintenance is December 2005 through May 2006 (there is potential for short testing during May). The next schedule for unit 1 maintenance is six months and the same for unit 2. Rehabilitation and timing of unit 1 and 2 depends on the release of funds by KfW and ARTF.

Some recent problems were as follows:

 

  • Rebuilding road from Kabul to Jalalabad diverted all traffic. Cars and trucks are crossing stream that provide cooling water for generators. Cooling water is muddy with a lot of clay in the water. This will cause problems with cooling of generators. Road construction will continue for at least 2 to 6 months.

  • Rubbish in Kabul river is so significant that cleaning system requires almost every hour to be run. There could be option to install additional cleaning system in upper side of the river.

  • There are gates, tunnel, etc. for installing additional 2 x 14 MW generating units; the power house has to be completely built.

 

Rehabilitation Program

 

Together with Mahipar rehabilitation is as a German grant ($15 million) plus ARTF ($7 million);  German grant is handled by KfW (Lehmayer); starting date was 7/3/2003; expected end of rehabilitation is 20/3/2007.  

 

Back to pe

 

 

 

 

 

 

 Panjshir Hybrid Power Sys

Click here

"The information provided on this web site is not official U.S. Government information and does not represent the views or positions of USAID or the U.S. Government."

Copyright © 2008 Afghan Energy Information Center

Privacy Policy