Faizabad survey report
FAIZABAD (BADAKHSHAN) ELECTRICAL
SYSTEM
Mission
headed by: Eng Shoaib Sahibzada
Mission
Members: Eng Faizi, Eng Omar and M.Naweed
Period
Covered: 8 up to 13 June / 2008
Introduction:
Badakhshan province is one of the North-
Eastern provinces of Afghanistan Faizabad is the Capital of this
historic province with a population of 58600 individuals and is
540 Km far from Kabul.
This province has 28 Districts and among
them only Sheghnan and Baharak Districts have Governmental
Electrical Power and the remaining districts have been
energized by National Solidarity Program (NSP).

Badakhshan Electrical Power
Department:
This department has been leads by Saed
Abdul Basir who is the Director of the mentioned office and
after him there are Technical Deputy Director (Mr Asadullah) and
Administrative Deputy director (Mr Noor Ahmad).
The mentioned department has 52
person personnel including the Sheghnan and Baharak Districs
personnel.
|
S/N |
Description |
Position |
Mobile Phone No. |
|
1 |
Saed Abul Basir Hosaini |
Director |
0799 285206 |
|
2 |
Asadullah |
Technical Deputy Diretor |
0799 863908 |
|
3 |
Noor Mohammad |
|
0700 748413 |

Electrical System:
FAIZABAD Capital of
Provice :
List of Step Up Transformers:
|
S/N |
Name of T/S |
Capacity (KVA) |
Voltage Ration |
Remarks |
|
1 |
Master plan |
120 |
0.4/10kV |
|
|
2 |
Diesel house |
630 |
0.4/10kV |
|
Consumer's list
|
Governmental |
Commercial |
Residential |
Mosque |
Important Building |
Total |
|
45 |
110 |
2771 |
24 |
50 |
3000 |
Sheehan
District:
There is one Micro Hydropower Plant that
has been constructed in 1986 with Capacity of 125 KW .
The usage of water of this plant is
alternatively it means during the day the water is used for
irrigation purpose and during the night for rotation of
Turbines.
This power is plant feeding 700 consumers.
Baharak
District:
According to declarations of Technical
deputy director of Badakhshan this District has been energized
by Imported Electrical power from Tajekistan by 35 KV
Transmission line with 250 KW capacity.
This is in Extension condition according to
recent agreement between Afghanistan and Tajekistan to will
enhance the mentioned capacity up to 500 KW.
Survey
AIM:
To find out the number, location of poles
which resist the construction work of Kishem FAizabad reod and
design a new reliable rout for the Electrical system of city.

ACHIEVMENTS:
We surveyed
5.5Km(63
)10 Kv and (32) 400v poles beside the road .
Out of above figures only (22 )10kv and (19) 400v poles to be replace
which are at the area (Right of Way) ROW at around
2.5km
area and resist the construction work for the udder construction
road.
|
Number
of Poles 10 kv
exist along the road |
Number
of Poles 400v
exist along the road |
Member of Poles
10 kv to be repace
|
Member
of Poles 400v
to be repalce |
|
63 |
22 |
32 |
19 |
Threes sources feeding the city :
1.
Micro Hydropower Plant
2.
Diesel generator of DABM
3.
Diesel generator of Private Sector
Most of consumer connected
direct to Gen set 400V wit more then 1 km distributer cable or
Overhead line system which cause of losses in the system.
Electrically detail is attached in PDF
attachment with (SLD)
The detail sketches of site in detail with
all dimensions include in 4 A1 graph papers will help us for
preparing plan for the system.

|